Paper question 24Solution(4 marks)The amount of work is measured in man-hours.Work needed =5 men×6 h/day×12 days=360 man-hours.3 men working 8 hours a day do 3×8=24 man-hours each day.Days needed =360÷24=15 days.More days =15−12=3 more days.Key point: Fewer men working for more hours: fewer men means more days (inverse proportion), more hours per day means fewer days. The question asks for how many more days, so subtract the original 12 days.