Question : 4
Total: 10
Solution:
What we are solvingThe Uganda Railway ran from Mombasa to Kisumu (Port Florence) on Lake VictoriaWork began at Mombasa in 1896 and the line reached Kisumu only in December 1901 (finished 1902-03)We must analyse the factors that slowed the constructionChapter: Colonial economy: transport and communication in East AfricaTopic: Construction of the Uganda Railway (1896-1902)Key ideasPurpose: link Uganda to the coast, end the slave trade, open the interior and secure the NileChief engineer: George Whitehouse; about 32,000 Indian labourers (coolies) were brought inLength about 935 km (582 miles), cost about 5.5 million pounds; critics called it the 'Lunatic Line'Model answerIntroduction: The Uganda Railway was built by the British from Mombasa to Kisumu between 1896 and 1902; its construction took longer than planned because of many physical, human and financial problems.1. Difficult terrainThe line had to climb the Taru desert, cross the Rift Valley escarpments (Kikuyu, Mau) and descend to the lakeSteep slopes needed viaducts, cuttings and temporary inclines, which took time2. Shortage of water and foodThe Taru desert had no water: water was carried in by train for workersFood for thousands of workers had to be imported3. Tropical diseasesMalaria, dysentery, jiggers, scurvy and ulcers killed or weakened many workersTsetse fly killed transport animals4. The man-eating lions of Tsavo (1898)Two lions killed many workers at the Tsavo river bridge siteWork stopped for months until Lt-Col J.H. Patterson shot them in December 18985. Shortage of labourLocal Africans were unwilling to work for low wages away from homeLabour had to be imported from India, which was slow and costly6. African resistanceThe Nandi under Koitalel arap Samoei attacked workers and stole wire, rails and bolts to make weaponsKikuyu and Maasai groups also clashed with workers and caravans7. Lack of materials and equipment locallyRails, sleepers, engines and tools came from Britain and IndiaMombasa port (Kilindini) had poor unloading facilities, causing delays8. Natural disasters: famine and heavy rainsFamine in 1898-99 and diseases such as smallpox weakened the people around the lineHeavy rains washed away embankments and bridges that had to be rebuilt9. Financial problemsThe cost rose far above the estimateThe British Parliament argued over each new grant, slowing payments10. Poor planning and communicationThe route was not fully surveyed before work beganMessages and supplies moved slowly along the growing lineAssessmentPhysical problems (terrain, water, disease, lions) caused the longest delaysHuman factors (labour, resistance) and money problems added to themConclusionThe Uganda Railway was delayed mainly by the harsh environment, disease and labour shortage, made worse by African resistance, supply and financial problems; yet it was completed to Kisumu in 1901.Answer: Difficult terrain, lack of water, diseases, Tsavo man-eaters, labour shortage (Indian coolies), Nandi resistance, imported materials, famine and floods, high costs, poor planning.Tip: Use dates and names (1896, Tsavo 1898, Koitalel arap Samoei, Kisumu 1901): they show precise knowledge.
© africaexams.com
Go to Question:
Advertisements