What we are solvingThe project has two conditions
The volume estimate must be within 0.5 percent
The spillway height must be correct to three decimal places
Decide whether construction should proceed
Suggest one way to make the volume estimate more reliable
Chapter: Numerical methods
Topic: the accuracy of an approximation
Concept and formulasA recommendation gives the decision first
Then it gives the evidence, each result against its requirement
The trapezium rule replaces the curve with straight lines
Narrower strips follow the curve more closely, so the error becomes smaller
Working: the evidence808 m3 against 810.67 m30.33%<0.5%Condition one is satisfied
h=3.438 m (3 decimal places)Condition two is also satisfied
Working: the improvementUse a smaller interval width, for example 1 metre
That gives 8 strips in place of 4
Halving the width cuts the error to about a quarter
ConclusionConstruction should proceed immediately, because both conditions are satisfied
The volume error is 0.33 percent, and the spillway height is 3.438 metres
For a more reliable volume, use more strips of smaller width
Answer: Proceed; use more strips
Tip: In a recommendation, state the decision first, then support it with your numbers