Concept:A direct cost can be traced to the job or product being produced. Direct expenses (other than materials and labour) include royalties and the hire of special plant or machinery for a particular job. Overheads are indirect costs that cannot be traced to one job, e.g. factory rent, supervisors' salaries, depreciation of general equipment.
Solution:A building construction company hires a crane for the building work it is doing. The hire charge is incurred for that construction (production) work and is charged directly to the contract/job, so it is a direct production cost (a direct expense, part of prime cost).
It is not a financial cost (interest, bank charges), not an administration cost (office expenses), and not an overhead, because it is traceable to the job.
Key point: The stored key gives (D) overhead cost, but hire of special plant for a job is the standard textbook example of a direct expense.
Answer:Option C (a direct manufacturing cost)