Concept:The System Development Cycle shows the ordered phases of building an information system.
Path II connects an early analysis stage to the later development stages.
Explanation:The path labeled II points to the phase where the logical requirements are converted into a technical blueprint.
This blueprint includes database structure, user interfaces, hardware needs, and program modules.
In the System Development Cycle, that phase is known as system design.
It comes after the feasibility study and before implementation.
Therefore, the correct identification of path II is system design.
Answer:C. system design